Go back to PK0-003 - CompTIA Project+ Certification Exam

Question :-

The project manager uses historical data to determine it takes two hours to install a piece of machinery. The current project requires twenty of the same machine to be installed. The project manager estimates it will take forty hours to install all the machines. This is an example of which of the following estimating techniques?
Parametric
Bottom-up
Rough order of magnitude
Top-down

Want to practice for PK0-003 - CompTIA Project+ Certification Exam ? Click here.