Go back to PK0-003 - CompTIA Project+ Certification Exam

Question :-

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?
Update the project plan to accommodate the changes.
Perform an impact analysis.
Organize a stakeholder meeting to review the changes.
Change the project scope to reflect the change request.