Question :-

Which of the following are benefits of formal project closure? (Select TWO).
Ensures the project complies with organizational goals
Allows lessons learned to be used in future projects
Ensures all pending contracts are closed
Assures buy-in from all project stakeholders
Distributes a new workload and tasks to all project team members