Go back to PK0-003 - CompTIA Project+ Certification Exam

Question :-

A project team is comprised of team members based in North America, Europe, the Middle East and the Far East. Which of the following is the MOST efficient means of reporting project updates to all team members?
E-mail to all team members
A daily web conference
A weekly conference call
Face to face meeting at a central location

Want to practice for PK0-003 - CompTIA Project+ Certification Exam ? Click here.