Go back to MB4-534 - SL 7.0 Installation and Configuration

Question :-

A batch was posted to period 03-2007 and should have been posted to period 02-2007. Which steps are required to correct the situation? Choose the 2 that apply.
Enter a batch with the same debits and credits as the original and post it to period 03-2007.
Edit the Period to Post on the original batch and run the Post Transactions process again.
Enter a batch with the opposite debits and credits and post it to period 03-2007.
Enter a batch with the same debits and credits as the original and post it to period 02-2007.

Want to practice for MB4-534 - SL 7.0 Installation and Configuration ? Click here.