JK0-017 - CompTIA E2C Project+ Certification Exam
Go back to
CompTIA
Example Questions
Which of the following are examples of a good business case for a new project? (Select Two).
Increased profit opportunity for the customer
Increased efficiency internally for the customer
A Pareto diagram focuses attention on which of the following?
Locating defects with the highest occurrence
Which of the following occurs during administrative closure?
Closing out contracts with vendors.
Which of the following is included within the RFP?
Request total cost for all work to be completed and procedures for replying to the bid.
A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?
Analyze the impact of the change.
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
Time zones for various work locations
Which of the following would be the impact upon a project if the CPI for the project is .75?
The project is over-budget.
A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?
Requires planning and execution to be completed in parallel.
After identifying the activities in a work package, which of the following is the NEXT step that a project manager should complete?
Estimate costs
The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?
Post-mortem
Which of the following would be a direct output of the initiating process group? (Select Two).
Project charter
Preliminary scope statement
Which of the following is a reason why the project kick-off meeting is important?
It will introduce the team to the projects goals and objectives.
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?
$600,000
To ensure that project status meetings are effective and productive, the project manager should:
publish an agenda prior to the meeting.
Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the success of the company. Which of the following actions should the project manager take NEXT?
Invite all of the stakeholders to a meeting to discuss project requirements.
Several project tasks cannot be completed because local resources are not available. The project manager has to outsource the work to find qualified resources. Which of the following risk responses is the project manager using?
Transference
Which of the following sequences represents the correct order for implementing a change request?
Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.
Which of the following would measure a project's validity?
Strategic alignment
The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?
ETC
Which of the following is the BEST way for an organization to obtain qualified vendors?
Use the established vendor approval process.
A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?
Review the plan with the team and develop a way to reduce the time
A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?
Determine if the project is in alignment with the company's strategic plan.
Which of the following describes a work breakdown structure (WBS)?
Is deliverable-oriented and hierarchical in nature
During which of the following process groups is the preliminary project risk assessment performed?
Planning
Information regarding training, extended support, and warranties are detailed in the:
Transition plan
Work must be overlapped and completed in parallel rather than sequentially within the critical path in order to meet the end date of the project. Which of the following would be utilized?
Fast-tracking
A project can be defined as which of the following?
A temporary endeavor limited by time or cost
Which of the following is a representation of the amount of money spent on project work at a point in time?
AC
An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000. Which of the following is the CPI of the project?
1.1
Which of the following is the correct formula for computing a projects SPI?
SPI = EV / PV
Which of the following is the method for determining the critical path of a project?
Examine the project schedule and calculate the total time taken for all scheduled activities, from commencement of the project to closure, with zero float.
Control limits would be found in which of the following plans?
Quality management plan
At a project milestone meeting, the project sponsor asked about a deliverable that is not on the project plan. Which of the following should the project manager do to compensate for this unmet expectation?
Review the scope with the sponsor.
The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?
Communication plan
In which of the following organization types is it LEAST likely that a conflict regarding competing demands for resources would take place?
Projectized
Which of the following is an example of risk mitigation?
Reduce the likelihood of the risk.
Which of the following may require a modification to the project scope baseline?
An approved project change request
The project charter is an output of which of the following project phases?
Initiation
The project has been terminated. Which of the following should be conducted with the project team before they are released?
Post-mortem analysis
Which of the following would be the BEST tool to estimate activity time durations?
PERT
Which of the following would be goals of an effective kick-off meeting? (Select Two).
To outline the communication plan
To set team member expectations
Which of the following are characteristics of an approved project charter? (Select Two).
Defines the project managers authority.
Validates the existence of a project.
Which of the following is an appropriate risk response for diverting a portion of the project risk?
Sharing
Which of the following elements does a project charter contain?
A project scope statement
Which of the following is included in the project scope document? (Select Two).
Assumptions
Constraints
One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation?
Arrange for training for the team member.
All of the following are taken into account when determining the critical path EXCEPT:
Resource limitations.
The project kick-off meeting is held:
at the end of the planning process.
Which of the following describes a work breakdown structure (WBS) dictionary?
A supporting document that provides more detail for the WBS components.
Which of the following describes the point in time when resources can be assigned to scheduled tasks?
When the work breakdown structure (WBS) is decomposed into work packages