Question :-

Verification and testing is part of most SAN implementations. One of the normal tests is to power off all the SAN components. What is the recommended sequence to remove power from the SAN components?
the same order in which the devices were powered on
tape libraries, switches and then storage
storage, servers and then switches
routers, storage and then switches