Go back to E20-555 - Isilon Solutions and Design Specialist Exam for Technology Architects

Question :-

An Isilon customer has two 5-node clusters, one for production and one for disaster recovery (DR). The customer's workflow is a SmartLock workflow and is replicated to the DR cluster through SyncIQ on an individual schedule. The customer needs to shutdown their production cluster for scheduled maintenance. Assume both clusters have identical shares, exports, user authentication, and that the client applications have been stopped and the DNS re-pointed. What is the correct method to start operations on the DR cluster?
Initiate Manual Failover of the SyncIQ Policy
Initiate Automated Failover of the SyncIQ Policy
No change to the SyncIQ Policy
Revert the SyncIQ Policy

Want to practice for E20-555 - Isilon Solutions and Design Specialist Exam for Technology Architects ? Click here.