Question :-

During the implementation phase of an Electronic Document Management System (EDMS) project, the Project Manager discovers that the storage system will not arrive by its targeted installation date. What is the next step?
Change the project Gantt chart to reflect the new expected date
Proceed as normal because the project schedule will resolve itself
Create a project change request and submit it to the project committee
Order a storage system from another vendor