During the project planning phase, it is essential for the consultant to obtain which one of the following?
A Gantt chart with all of the correct resources on the project
A work breakdown structure with all of the tasks required
A cultural change document with steps to ensure a smooth transition
Documentation of the clients acceptance for each part of the project