The technical manager in an imaging/document management company is responsible for all aspects of the client's system installation. What are three things that will ensure all installations are completed in a consistent manner?
A written budget, written scope of work, workflow diagrams.
A project plan, the system integrator's reputation, detailed budget.
A written implementation plan, design reviews, post-implementation review.
Phone consultations, contract vendor and customer, approved by the customer's CEO.