Question :-

An example of a possible configuration of Security Groups: Group Site 1 Site 2 Site 3 Site 4 Purchase Order Limit AYYNN $5000 BYNNN $10000 CNNYN $15000 DYNNY $7000 If a user belongs to Security Group A, Security Group B, and Security Group D, what is the correct purchase order limit for that user?
$5000
$10000
$12000
$22000