Question :-

Scenario: You met with the Network Administrator twice and learned that their WAN circuits are at or nearing capacity between several sites. You asked for more detailed information regarding network usage, but it has not yet been provided. You raised this issue several times to the customer project manager and even the project sponsor. This information is required for both the assessment and upcoming design. Which action should you take in response to this delay?
You should include this in the Issues section of the weekly project status report.
You should conclude the assessment portion of the project and indicate that the information was unavailable in all areas related to network traffic.
You should issue a risk memo to the Network Administrator.
You should issue a risk memo to the project manager and project sponsor.