Go back to PRF - PRINCE2 Foundation

Question :-

Which of the following statements about quality assurance and Project Assurance is true?
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Want to practice for PRF - PRINCE2 Foundation ? Click here.