Go back to PRF - PRINCE2 Foundation

Question :-

Which statement describes the Implement' step within the recommended risk management procedure?
Take planned action to respond to a risk
Implement the responsibilities for risks defined in the Risk Management Strategy
Assess the proximity of a risk
Identify the level of risks that can be tolerated by the project

Want to practice for PRF - PRINCE2 Foundation ? Click here.