Question :-

Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits laid, 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true