Which is an objective of the Managing a Stage Boundary process?
Understand what has gone well and what can help the next stage
Review and approve the next Stage Plan
Assure the Project Board that all project products have been completed and approved
Prepare an Exception Report to advise the Project Board of a forecast deviation from tolerance