Question :-

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Which of the following is least likely to improve a large earthmoving contractor's productivity?
Using apprentice operators to save labor costs
Starting summer work in the early morning hours to minimize work during peak heat periods of the day
Remove underground hazards prior to excavation work
Replacing old excavators with new, larger excavators