Question :-

A work breakdown structure (WBS) is developed because:
It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.
It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans
It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup
It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence