Question :-

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. The following is NOT an advantage of the critical path method:
The ability to determine cost overruns of critical path activities
The ability to identify activities that cannot have their schedules slip if the desired project end date is to be achieved
Reveals activities that additional resources need to be dedicated toward
The ability to show slippage in the progress of key activities