A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has a schedule performance index of 0.80. What would you advise the management about the scheduled completion date?
Project will be completed in 20 more weeks
Project will be completed this week - on schedule
Project will be completed in 4 more weeks
Project will be completed in 12.8 more weeks

Want to practice for CCE-CCC - Certified Cost Consultant / Cost Engineer (AACE International) ? Click here.