Go back to CCE-CCC - Certified Cost Consultant / Cost Engineer (AACE International)

Question :-

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data. Resource planning must take all of the following into account except:
Types of materials, equipment and labor skills required to complete the project
Cash flow (expenditures) limitations for completing work on the project
Time available to complete the project
Earned value techniques established for the project

Want to practice for CCE-CCC - Certified Cost Consultant / Cost Engineer (AACE International) ? Click here.